Single Piece Flow
SMALL
MOTOR MANUFACTURING COMPANY
INTRODUCTION OF SINGLE PIECE FLOW
THE COMPANY
The company are a small motors manufacturer based in the North East
of England. Turning over around £20m with just over 100 people
they were faced with increasing competition from abroad. They had
to find ways of increasing productivity and decreasing costs. This
meant that through increasing throughput and reducing the lead-times
the cost of non-quality could be reduced and the company became
more competitive.
THE ASSIGNMENT
The assignment was to review the production line for the assembly
of H50 motor line. This line was run on batch production and as
a result had a large amount of work in process. The operators did
not work as a team and everyone worked at his or her own pace. Productivity
was not as optimum as it could be and there was no team spirit or
goals set.
Customer changes were frequent even after the job had started resulting
in rework and lost production time. The activity took place over
a 4 ½ day project with a follow up after a few weeks for
items that couldn’t be completed in the time frame. The target
was to review the activity and improve productivity, reduce WIP
and therefore the lead-time through the area.
INITIAL ACTIVITIES
The initial review included the completion of a 5S audit and a tour
by the cross functional team to understand the situation. Once the
team understood the requirements following some education in lean
thinking, problem solving and creative thinking the team set about
reviewing the process and developing it having taken part in a simulation
game to highlight what was possible. A detailed process mapping
session and collecting of some baseline data such as amount of WIP,
process dynamic cycle time and distance travelled by operators and
the part was then completed. All the possible problems and issues
associated with the process where then brainstormed.
The team then developed an approach to implement one-piece flow.
The reasons for the implementation of one-piece flow were as a result
of the product types, the need to reduce WIP and increase throughput
while reducing lead-times.
FURTHER ACTIVITIES
The team implemented the solutions through the use of removal of
convoy belts, developing part delivery systems that could be fed
from behind to enable stations to be implemented. The team also
set up new roles and responsibilities for the team, with the team
leader becoming the materials handler, a person who filled in when
required for breaks etc as well as the normal development and people
tasks. The area used all the principles of 5S as well as putting
in Kanbans and team working. The activity was then trailed and all
the operators where trained by the team through the use of the simulation
game and presentation slides.
BENEFITS
Apart from educating and training the whole team in Lean principles
and how to implement it the cross functional team delivered real
bottom line savings. The intangible benefits included operators
who were happier. Tangible benefits included: -
| Key Measures | Before |
After |
Improvement |
| WIP (parts) | 95 |
19 |
80% |
| Operations | 28 |
21 |
39% |
| Walking distance (m) | 3320 |
1430 |
57% |
| Parts traffic (m) | 149 |
128 |
14% |
| Units produced (parts) | 234 |
320 |
36% |
| Process dynamic time (mins) | 138 |
29.5 |
79% |
It is difficult to show the savings in £ as the selling price was so variable and the company only wanted to review in terms of up time of the machine but as the machine was a bottle neck then capacity was increased substantially and therefore so was turnover.
For
more information please contact Strategic
Business Partners.